Weekly Road Report for the Week of July 20 -26

Intersection of SE 15th Street and SE Bronzewood Avenue

Intersection of SE 15th Street and SE Bronzewood Avenue will have utility relocations.

Single lane closures with flagging, July 20 – 24 from 9 a.m. – 3:30 p.m.

SE 15th Street

SE 15th Street between Bear Creek and Wilson Ave for franchise utility work.

Single lane closures with flagging, July 23 – 24 from 8 p.m. – 6 a.m.

NW 8th Street

NW 8th Street between NW Portland Avenue and NW Quincy Avenue will have a watermain replacement.

Full road closure with local access only, July 20 – August 31 from 7 a.m. – 3 p.m.

Intersection of NE 11th Street and NE Norton Avenue

The intersection at NE 11th Street and NE Norton Avenue will have roadway and sidewalk infrastructure installations.

Full intersection closure with detour, July 20 – August 25

Cooley Road and Ranch Village Drive

The City of Bend is constructing a new gravity sewer main along Cooley Road and Ranch Village Drive. This new line will connect to existing infrastructure west of the Cooley Road and 18th Street intersection, optimizing our community’s sewer system. Various road impacts will be required for the project including:

  • Cooley Road (Ranch Village Drive to the 18th Street/Cooley Road roundabout) One lane will be closed, with two‑way traffic maintained through flagging.
    Schedule: July 13 – Fall 2026
  • Ranch Village Drive (Double Peaks Drive to Cooley Road) Closed to through traffic; local access only.
    Schedule: Early August – End of October
  • Egypt Drive (Ranch Village Drive to 18th Street) Closed to through traffic; local access only.
    Schedule: Estimated for the last week of August

2026 Street Preservation

Various Streets across the City will have chip seal work with multiple lane closures from 7/20 through 7/25 (expect delays), work to occur between 7 a.m. – 6 p.m. Expect rolling, short term closures on sections of these roads:

  • Monday, July 20: Summit West neighborhood between NW Brickyard Street and NW Summerhill Drive
  • Tuesday, July 21: NE Purcell Boulvard and sections of NE Revere Avenue
  • Wednesday, July 22: Mt. Washington Drive
  • Thursday, July 23: Mt. Washington Drive and sections of NE Revere Avenue
  • Friday, July 24: NW Crossing Drive and sections of Mt. Washington Drive
  • Saturday, July 25: NE Olney Avenue

More info on the streets that will be impacted:

Street Preservation Projects

Franklin Avenue Improvements Project

This initial work is focused on replacing aging water pipes from 1st Street to 4th Street, begins July 6th. Street impacts:

  • Daytime work with lane reductions and flagging required to maintain traffic through the corridor, alternate routes should be taken to avoid delays
  • Temporary westbound closure of Franklin Avenue between 3rd Street and 4th Street begins July 6th and tentatively ends mid-August, detour provided

Franklin Avenue Improvements Project

NE 2nd Street

Water Main Replacement Project – Aging water main will be repaired and replaced along NE 2nd Street.

Phase 1 Work begins July 6 – End of August. Street affected:

  • Ongoing – Phase 1: 2nd Street to be closed from Olney Ave to Norton Ave with local traffic allowed through
  • Future – Phase 2: Traffic control anticipated to shift into Phase 2 (2nd from Norton to Lafayette) on July 29
  • Phase 1 will still have restricted access with current work area acting as a staging area

Intersection of SE 15th Street and Ferguson Road

Intersection of SE 15th Street and Ferguson Road will have roundabout construction.

Full intersection closure with detour, June 22 – Fall 2026

Criterion Race Series (Special Event)

This special event is a five-week race event occurring every Wednesday from June 24 – July 22. The event will close a few NW City streets (listed below). A detour will be in place for the event.

  • NW Crossing Drive between NW Elwood Lane and NW Skyline Ranch Road
  • NW Elwood Lane between NW Crossing Drive and NW Lolo Drive
  • NW Lolo Drive between NW Elwood Lane and NW Skyline Ranch Road
  • NW Skyline Ranch Road between NW Lolo Drive and NW Crossing Drive

Bend Bikeway Project, SE Area

The Bend Bikeway Project provides safer connections for pedestrians and bicycles traveling between neighborhoods, schools, places of work, parks and trails across town. Improvements will include a new shared use path with work primarily occurring as shoulder work, with intermittent single lane closures and flagging.

Work begins June 24 – Fall 2026. Streets affected:

  • SE 9th Street between SE WIlson Avenue and SE Reed Market Road
  • SE 15th Street between the Larkspur park and Bronzewood Ave
  • NE Bear Creek Road between NE Alpenview Lane and SE Craven Road

Bend Bikeway Project

NE 18th Street

NE 18th Street at the intersection with the Yeoman Road extension will have roadway and pedestrian improvements.

Northbound Lane closure with detour (southbound accessible), June 15 – July 30

NW Crossing Farmers Market (Special Event)

Special event occurring every Saturday, May 30 – September 26. Multiple road closures related to event:

  • NW Crossing Drive between Mount Washington Drive and NW Crossing Drive (Circle)
  • NW John Freemont Street between NW Ordiway Avenue and NW Fort Clatsop Street
  • NW Fort Clatsop Street between NW Ordway Avenue and NW John Freemont Street

Windsor Drive

Windsor Drive between Brosterhous Road and Woodside Court for a sewer main installation (part of City Septic to Sewer Program).

Full road closure with local access only, April 27 – End of August

King Hezekiah and Fargo Sewer Project

Various Road closures will be required for the installation of new sewer mains. Road closures listed below:

  • SE King Hezekiah Way between SE 15th Street and King Jehu, June 15 – End of October

King Hezekiah and Fargo Sewer Project

Ponderosa Street

Ponderosa Street between SW Atwood Ave and Granite Drive will have roadway construction.

Full road closure with detour, June 5 – July 28

Magnolia Lane

Magnolia Lane between Hearthstone Lane and Ferguson Road will have infrastructure improvements.

Full road closure with local access only until August 15

Butler Market Corridor Improvements

This project will construct a new single lane roundabout at the intersection of Butler Market and Wells Acres Road, and pedestrian and bicycle improvements on Butler Market between the 8th Street roundabout to Brinson Blvd.

Roadway impacts:

  • Butler Market Road between NE Brinson Boulevard and NE 8th Street will have a westbound lane closure with detour.

Construction is well underway and is expected to be completed in September of 2026.

Butler Market Corridor Improvements Project

NW Harriman Street

NW Harriman Street between NW Kearney Avenue and NW Greenwood Avenue for infrastructure work associated with the Deschutes County Courthouse.

Full road closure through July 31

Upcoming Roadway Impacts:

Highway 20

ODOT Overnight Paving – Paving will occur along Highway 20 between Robal Lane and Mervin Samples Road.

Work occurs late July – early August

Ferguson Road

Ferguson Road between Ferguson Court and Magnolia Lane will have final paving.

Single lane closure with flagging, July 27 – 29 from 9 a.m. – 3:30 p.m.

 


Work schedules are dependent on weather conditions and other factors. Always exercise increased caution within construction zones. Drivers should use designated detour routes. Nearby residential streets are for local traffic only.

Any road closure not listed within this report, please submit a service request to notify the City of any potentially unpermitted work within City right-of-way. Please visit the Transportation and Mobility Department to submit.


Contact Information

Alex Pelayo, Project Engineer
541-323-8556, apelayo@bendoregon.gov

For Street Preservation related questions:
Paul Neiswonger, Streets Supervisor
541-317-3035, pneiswonger@bendoregon.gov

View All News