Actualización sobre el proyecto de alcantarillado de Admiral y King Jehu – 17 de marzo de 2022
TENTATIVE CONSTRUCTION (KING HEZEKIAH WAY)
- The construction crews are available to begin work a little earlier than anticipated. Notices of upcoming construction were hand-delivered on 3/16/2022 to each property directly adjacent to the construction limits in the King Hezekiah section. Construction notices for subsequent sections of the project limits will be delivered as the schedule progresses forward.
- Pothole activities will occur in late Marzo/early Abril.
- Erosion control devices (straw wattle, construction fencing, etc.) and traffic control setup (signs, barricades, etc.) will occur in late Marzo/early Abril.
- En el suelo hay marcas pintadas que indican dónde se encuentran las instalaciones subterráneas.
- Minor tree trimming and clearing activities may occur.
SEWER LATERAL LOCATIONS
Sewer laterals (also known as stub-outs) are marked at your property with a wooden stake and a green lath. Several of you reached out to me to change the location of your sewer lateral. Please note, we have not updated the stakes yet. We will update the stakes towards the start of construction. I will follow up with you once the stakes are updated. Please do not move any project stakes. All lateral relocation requests are highly encouraged to be submitted by Marzo 31, 2022. Please use my contact information below to submit questions, comments, or concerns.
FOTO DEL PROYECTO
Below is an example of pothole activities using a vacuum truck. Water is used to dig and break through the ground, and the vacuum sucks up the soil into a debris tank. Potholing is typically used to investigate utilities belowground in a sensitive, non-intrusive manner.

CONTROL DE TRÁFICO
Traffic control will be installed in late Marzo/early Abril. The closure area (on the map below in red) and detour (blue dashed line) is shown below. Local access will be provided on King Hezekiah Way and King Solomon Court for homeowners living on those streets. Please proceed with caution when driving in the construction zone.

Carretera cerrada al tráfico de paso / Solo acceso local
El tráfico local (es decir, los propietarios que viven junto a la zona de obras) puede pasar esta señal para acceder a sus entradas o viviendas. Se ruega extremar la precaución al circular por la zona de obras.

Road Closed/Do Not Enter
No one is permitted to drive past these signs.

RECURSOS
- Para obtener más información específica sobre la construcción de este proyecto, visite la página webwww.bendoregon.gov/admiral-king-jehu.
- Para obtener más información sobre el programa «De fosa séptica a alcantarillado», las tasas, otros proyectos, los permisos, etc., consulte la página webwww.bendoregon.gov/septictosewerprogram.
CONTACTO DEL PROYECTO
Alex Doza, P.E., Assoc. DBIA | City of Bend, Project Engineer – adoza@bendoregon.gov or 541-678-2597