Actualización sobre el proyecto de la red de abastecimiento de agua de Awbrey Butte – 16 de junio de 2023
El proyecto de mejora de la red de abastecimiento de agua de Awbrey Butte mejorará la capacidad de Bend para suministrar agua a toda la ciudad y aumentará la resiliencia y la fiabilidad del sistema mediante la instalación de aproximadamente 4,25 millas de tuberías.
Project Update – junio 2023
Construction of Phase 1 improvements began in early junio. Phase 1 is being constructed in stages to minimize traffic impacts and expected to be completed in Marzo 2024.
The City is committed to keeping neighbors informed throughout construction with bi-weekly updates. In advance of construction activities in your neighborhood, residents will receive a more detailed notification with specific information regarding construction impacts.
You Are Invited!
Portland Avenue Project Informational Meeting
You Are Invited!Portland Avenue Project Informational Meeting
Westside Church
junio 27, 2023
5 p.m. – 6:30 p.m.
The informational meeting begins at 5:00 p.m., with a brief presentation at 5:15 p.m.
The City of Bend will host an informational meeting on junio 27 to share information about potential improvements on Portland Avenue. The meeting will be held in person at Westside Church, 2051 NW Shevlin Park Road, from 5:00 p.m. to 6:30 p.m., with a brief presentation at 5:15 p.m. The same information and exhibits will also be available online at bendoregon.gov/awbrey-waterline beginning junio 27. Community members are invited to provide feedback by completing an online survey open from junio 27 through julio 11. Survey link will be available on the website.
Upcoming Activities
|
Activity |
Area(s) |
Qué puedes esperar |
Expected Timeframe |
|
Phase 1 construction on Awbrey Road at Saginaw Avenue intersection |
Saginaw Avenue and Awbrey Road |
Single-lane closure during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected. |
junio 1 to Mid-junio* |
|
Installation of waterline at Utica Avenue and Second Street Intersection |
Utica Avenue and Second Street intersection |
Single-lane closures controlled by flaggers during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected. |
junio 1 to Late junio* |
|
Installation of waterline on Utica Avenue |
Utica Avenue between Awbrey Road and Second Street |
Single-lane closures controlled by flaggers during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected. |
Mid-junio to Late junio* |
|
Installation of waterline on Second Street |
Second Street between Utica Avenue and Vicksburg Avenue |
Single-lane closures controlled by flaggers during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected. |
Mid-junio to Early julio* |
|
Installation of waterline on Vicksburg Avenue |
Vicksburg Avenue between Awbrey Road and First Street |
Single-lane closures controlled by flaggers during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected.
|
Early julio to Mid-julio* |
|
Awbrey Road |
Awbrey Road between Portland Avenue and Saginaw Avenue |
A full detour will occur on Awbrey Road. Traffic will be detoured on Saginaw Avenue and Second Street. |
Mid-Late julio – Mid Septiembre* |
|
*Periodic asphalt and concrete restoration work expected. |
|||
Thank you to everyone who joined us for “Coffee with the Contractor” on junio 2!

WHAT TO EXPECT DURING PHASE 1 CONSTRUCTION
Nos comprometemos a reducir al mínimo las molestias que las obras puedan causar a los vecinos y a los miembros de la comunidad. Nuestro plan de gestión de las obras incluye medidas para minimizar las molestias derivadas del tráfico, el ruido, el polvo y otros aspectos relacionados con las obras.
Within Phase 1, there are three subprojects:
- Subproject 1: Awbrey Road Waterline Improvements: junio 2023-Octubre 2023
- Subproject 4: Awbrey Reservoir Outlet: noviembre 2023-Diciembre 2023
- Subproject 5: NW Ninth Street Waterline Improvement: noviembre 2023-Marzo 2024
Subprojects 3 and 6 on the map below have been tentatively removed from the construction schedule to re-evaluate project priorities. They may be included in a future construction project.

Construction will generally occur Lunes to Viernes from 7:00 a.m. to 5:00 p.m., with extended hours and weekends (as needed and on a very limited basis). A detour will occur on Awbrey Road mid to end of julio. Temporary No Parking signs will be installed in advance of the detour along 2nd Street to provide adequate access. The remainder of the work will involve single-lane closures controlled by flaggers during weekdays between 7 a.m. – 5 p.m. Traffic delays are expected.
Any work that includes crossing driveways will be coordinated with residents one day prior to work commencing and again on the day of work before being impacted. Emergency Medical Services, mail, garbage, and delivery services will have continued access.
If there is a planned shutdown of the water service that will impact your property, you will be notified ahead of time. If there are delays to the schedule, a project representative will be on-site to notify you.
The construction is taking place within the Public Right-Of-Way. Please visit the project website to learn more about public Right-Of-Way
You may also monitor current and upcoming detours and closures at www.bendoregon.gov/traffic.
Project Map – subject to change

For additional information, Subproject details, or to sign up for regular project updates for the Awbrey Butte Waterline Improvement Project, please visit: ww.bendoregon.gov/awbrey-waterline.
CALENDARIO PROVISIONAL DEL PROYECTO
El diseño y la construcción del proyecto se llevarán a cabo por fases. El calendario que figura a continuación se actualizará a medida que se disponga de más información y está sujeto a cambios. Este proyecto utiliza un método de ejecución alternativo conocido como «diseño y construcción progresivos», que implica la selección simultánea del contratista y del ingeniero. Por lo tanto, algunas fases del diseño se solaparán con partes de la construcción a lo largo del proyecto. Es posible que las propiedades individuales no se vean afectadas durante todo el periodo de las fases de construcción que se indican a continuación.
Calendario provisional de diseño:
Subprojects 1, 3, 4, 5, & 6: Septiembre 2022 – fall 2023
Subprojects 2, 7, 8, & 9: noviembre 2022 – spring 2024
Calendario provisional de obras:
Subproject 1: junio 2023 – Octubre 2023
Subproject 2: early 2024 – late 2024
Subproject 4: noviembre 2023 – Diciembre 2023
Subproject 5: noviembre 2023 – Marzo 2024
Subproject 7: early 2024 – fall 2024
Subproject 8: early 2024 – winter 2025
Subproject 9: early 2024 – fall 2024
¿TIENES ALGUNA PREGUNTA O COMENTARIO?
Teléfono del proyecto: 541-382-3264
Correo electrónico del proyecto: awbreywaterline@bendoregon.gov
Sitio web del proyecto: www.bendoregon.gov/awbrey-waterline
Personas de contacto del proyecto:
Jake Sherman, ingeniero de proyectos sénior
ShanRae Hawkins, coordinadora de participación ciudadana