Actualización del proyecto de mejora del alcantarillado de Ferguson – 20 de julio de 2023
PRÓXIMAS OBRAS PREVISTAS
- Crews continue to excavate and install sewer pipe, maintenance holes, and sewer laterals to the east along Ferguson Road.
- The southbound Ladera Road at Ferguson Road is closed for the week of julio 17 for sewer installation and is anticipated to be open early next week. Ferguson Road is closed to eastbound traffic from Ladera Road to the east of Magnolia Lane. Please continue to obey all traffic signs and drive with caution through the construction zone.
- Crews will be pouring concrete intermittently as part of the sidewalk and driveway restorations.
- The Ridgewater II pump station is now decommissioned, and gravity sewer is live along Ferguson from that point and to the west.
- The Camden Park pump station is now decommissioned, and the gravity sewer is live up to Cottonwood Drive.
- Those properties located along Ferguson between the Ridgewater II pump station and Cottonwood Drive that received a new sewer service with this project will receive a Notice of Operational Completion in the mail. This is the formal notice that sewer is legally available to the property.
- Additional Franchise Utility relocations are occurring just west of Cottonwood Dr. Traffic will be maintained in the westbound direction.
- For those along Ferguson currently served by septic and receiving a new sewer lateral with this project, visit www.bendoregon.gov/septictosewerprogram for more information on connecting to sewer after receiving the Notice of Operational Completion.
QUÉ PUEDE ESPERAR DURANTE LAS OBRAS
- Durante las obras se producirán ruidos, polvo y vibraciones.
- Tenga en cuenta los posibles retrasos por el tráfico y prevea más tiempo al planificar su trayecto. Conduzca despacio al pasar por la zona de obras.
- Although we make every effort to maintain services during construction, you may experience a temporary outage due to an inadvertent occurrence. For example, if you experience an internet outage, please notify the project contact (provided below) directly so that the project team can ensure it’s being remedied.
- Las paradas de autobús escolar situadas a lo largo de Ferguson Road seguirán en su sitio. Los usuarios del autobús podrán esperar en la parada y subir al autobús. Habrá un señalizador en el lugar para ayudar en caso necesario.
- For those who receive garbage pick-up along Ferguson Road, please take your bins to the edge of your frontage on the day of or prior to your garbage pick-up. The contractor will wheel them to the edge of the work zone if they are inaccessible to the garbage service at the end of the work shift.
- Para quienes reciben correo en la calle Ferguson Road, la empresa contratista trasladará temporalmente su buzón si las obras impiden el acceso al mismo. Los buzones que se trasladen volverán a colocarse en su ubicación original una vez finalizadas las obras.
CONTROL DE TRÁFICO
Starting early next week, Ferguson Road will be closed to eastbound traffic from east of Ladera Road to east of Magnolia Lane. Note that Sarah Drive will be closed; please access Sarah Drive through Ladera Road. The south intersection of Ladera Road and Ferguson Road will be temporarily closed for the week of julio 17 and is anticipated to re-open early next week. Ferguson road traffic is now two-way between 15th Street and Ladera Road. The closure and detour maps are shown below.
Local access to side streets and driveways off Ferguson Road, which do not have a secondary access point, will be maintained during construction. ALL traffic within the bounds of the closure is flowing westbound. You may experience delays of up to 20 minutes when driving through the construction zone. Please reduce speeds and proceed with caution. We appreciate your ongoing patience. Sign up to get real-time information about major milestones related to traffic closure staging by texting Ferguson to 503-483-5506.
Ferguson Road Eastbound Closure, Stage 3 of 4
Desvío en Ferguson Road en dirección este, resumen (todas las fases)

FOTO DEL PROYECTO
Below is a photo of workers carefully lowering a sewer maintenance hole base section into a trench. This maintenance hole is one of fourteen that are being installed as part of the Ferguson Sewer project.

RECURSOS
Página web del proyecto:www.bendoregon.gov/fergusonsewer
Persona de contacto del proyecto:
Alex Doza, ingeniero colegiado (PE), DBIA – Ingeniero de proyectos del Ayuntamiento de Bend – adoza@bendoregon.gov o 541-323-8595