Midtown Crossings Project Update – Marzo 19, 2025

Second Street Improvements Update 

TRAFFIC ALERT: Second Street Detour Changes to One-way Northbound Only – Effective Marzo 24

Crews are almost complete with Stage 1 on Second Street. They will move work to the westside of Second and continue working to build curbs and sidewalks, and then pave the new road in Stage 2.  

Starting Marzo 24, construction work will move to the west side and traffic will switch to the east, travelling northbound only, from Franklin Ave toward Greenwood Ave.

Second Street construction detour beginning MAR 24 2025 includes third street and business access down first street and side streets

Stage 2: Marzo 24 through Mayo 2025

  • To reduce impacts, work will be contained to one side of the street when possible.
  • We’ll now work on the west side, with the east side reopening to one-way northbound traffic (Franklin to Greenwood).

Business Access Remains Open During Construction

  • Vehicles approaching from Greenwood will need to detour to Third Street to travel north from Franklin Avenue, or take First Street.
  • Cross traffic on Hawthorne, Irving, Greeley or the alleys will need to turn north on Second and may not be able to cross Second while work is performed.

Keep it Local, Even Through the Detour!

Thank you for continuing to support businesses during construction.

 

Work is expected to be completed in late Mayo. Please keep in mind, weather conditions may impact this timeline. 


The Midtown Crossings Project is improving east-west travel between downtown and the Central District and includes improvements to four key connections in the area: Greenwood Avenue, Hawthorne Avenue, Franklin Avenue, and Second Street.
   

Mapa de las áreas del proyecto Midtown Crossings

Learn more about all the Midtown Pedestrian and Bicycle Crossings projects at bendoregon.gov/midtowncrossings.

If you have questions about this project, feel free to contact the project team at (541) 323-0771 or midtownxings@bendoregon.gov

Panel de control de bonos GO para transporte 2020

The Midtown Pedestrian and Bicycle Crossings Project is partly funded by the voter approved 2020 Transportation GO Bond. Explore the GO Bond Dashboard to find the latest GO Bond budget and project status information. Visit bendoregon.gov/gobond.


Información sobre alojamiento para personas con discapacidad 

To obtain this information in an alternate format such as Braille, large print, electronic formats, etc. please contact Todd Johnson at 541-323-0771 or midtownxings@bendoregon.gov. Relay Users dial 7-1-1.

Ver todas las noticias