Murphy Corridor Improvements Project Update – Agosto 27, 2021
Gracias por su interés en el proyecto de mejora del corredor Murphy.
Construction Activities – Week of Agosto 30
- Crews are pouring end panels at the BNSF bridge abutments and forming sidewalks and rails in preparation for pouring concrete after Labor Day.
- Work will begin on the retaining walls between the extension of Brosterhous Road and the BNSF bridge overcrossing.
- Crews will continue pouring sidewalks and ramps south of the Brosterhous Road roundabout near the train trestle along Brosterhous Road.
- Installation work will continue on the water main at the Brosterhous Road roundabout.

Above: Murphy Road extension between Brosterhous Road and the new bridge over the railroad.

Above: Bridge work occurring over the railroad looking east.
En la página webwww.bendoregon.gov/traffic se puede consultar un mapa interactivo con los cierres y desvíos.
Si tiene alguna duda, comentario o pregunta, póngase en contacto con el equipo del proyecto llamando al (541) 322-9919.
Información sobre adaptaciones para personas con discapacidad
Se ofrecen servicios de interpretación en lengua de signos, dispositivos de ayuda auditiva y materiales en formatos alternativos, como braille, letra grande, formatos electrónicos y CD, así como cualquier otra adaptación, previa solicitud. Para obtener esta información, póngase en contacto con el equipo del proyecto enMurphyProjectTeam@bendoregon.govo en el (541) 322-9919; los usuarios del servicio de retransmisión deben marcar el 7-1-1 y el (541) 385-6676.
Ver todas las noticias