Construction Activities – Week of Agosto 30

  • Crews are pouring end panels at the BNSF bridge abutments and forming sidewalks and rails in preparation for pouring concrete after Labor Day.
  • Work will begin on the retaining walls between the extension of Brosterhous Road and the BNSF bridge overcrossing.
  • Crews will continue pouring sidewalks and ramps south of the Brosterhous Road roundabout near the train trestle along Brosterhous Road.
  • Installation work will continue on the water main at the Brosterhous Road roundabout.

An aerial photo overlooking the extension of Murphy Road between Brosterhous Road and the new bridge over the railroad.
Above: Murphy Road extension between Brosterhous Road and the new bridge over the railroad.

An aerial photo overlooking bridge work occurring over the railroad looking east.
Above: Bridge work occurring over the railroad looking east. 

En la página webwww.bendoregon.gov/traffic se puede consultar un mapa interactivo con los cierres y desvíos.

Si tiene alguna duda, comentario o pregunta, póngase en contacto con el equipo del proyecto llamando al (541) 322-9919.

Información sobre adaptaciones para personas con discapacidad

Se ofrecen servicios de interpretación en lengua de signos, dispositivos de ayuda auditiva y materiales en formatos alternativos, como braille, letra grande, formatos electrónicos y CD, así como cualquier otra adaptación, previa solicitud. Para obtener esta información, póngase en contacto con el equipo del proyecto enMurphyProjectTeam@bendoregon.govo en el (541) 322-9919; los usuarios del servicio de retransmisión deben marcar el 7-1-1 y el (541) 385-6676. 

Ver todas las noticias