Murphy Corridor Improvements Project Update – julio 31, 2021

Gracias por su interés en el proyecto de mejora del corredor Murphy.

Notice: Crews will be working Saturdays on the BNSF bridge overcrossing and Murphy Road extension.

Construction Activities – Week of Agosto 2

  • Work on the Mechanically Stabilized Earth (MSE) retaining walls will include procuring precast panels.
  • Crews will continue backfill work on the substructure “bent” units that support the BNSF bridge overcrossing. 
  • Crews will begin installing lighting conduits on the bridge overcrossing. 
  • Continuará la instalación de pozos de drenaje pluvial y de pozos de mantenimiento a lo largo de Murphy Road.

An aerial photo looking south over the retaining wall for the new Murphy Road extension.
Above: Retaining walls for new Murphy Road extension (looking south)

An aerial photo looking south over the new Murphy Road bridge deck.
Above: New Murphy Road bridge deck (looking south)

En la página webwww.bendoregon.gov/traffic se puede consultar un mapa interactivo con los cierres y desvíos.

Si tiene alguna duda, comentario o pregunta, póngase en contacto con el equipo del proyecto llamando al (541) 322-9919. 

Información sobre adaptaciones para personas con discapacidad

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic formats & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676.

 

Murphy Project Team: (541) 322-9919 | MurphyProjectTeam@bendoregon.gov

Project Website: https://www.bendoregon.gov/murphyproject

Ver todas las noticias