Weekly Road and Traffic Report for the Week of junio 23-29

For the Week of junio 23-29:

  • SW Roosevelt Avenue between SW Sisemore Street and SW Chamberlain Street for infrastructure installation, full road closure with local access only, junio 23 – 27.
  • Hunnel Road between NW Henry Avenue and NW Robal Lane for service installations, single lane closure with flagging, junio 23 – 26, 8:30 a.m. – 4:00 p.m.
  • Criterion Race Series (special event) – This special event is a five-week race event occurring every Miércoles from junio 25 – julio 23. The event will close a few NW City streets (listed below). A detour will be in place for the event.
    • NW Sacagawea Lane between NW John Freemont Street and NW Meriwether Place.
    • NW John Freemont Street between NW Sacagawea Lane and NW High Lakes Loop.
    • NW High Lakes Loop between NW John Freemont Street and NW Meriwether Place.
    • NW Meriwether Place between NW Sacagawea Lane and NW High Lakes Loop.
  • Granite Drive between Poplar Street and Ponderosa Street, road closed with detour route, junio 24 – Agosto 8.
  • Street Preservation – Various Streets within the west, south, and north of Bend will have a slurry seal. This is a maintenance treatment to prolong roadway longevity. Full street closures with limited local access only during its duration (expect delays). junio 18 – 25 (weather dependent). Learn more at the Street Preservation webpage.
  • Staats Waterline Project– Replacement of aging water lines, upgraded hydrants and stormwater infrastructure, and pavement restoration along its entirety. Daytime closures of the roadway will occur during daytime hours (7:00 a.m. – 6:30 p.m.), junio 9 – End of Agosto. Street closures listed below.
    • NW Staats Street between NW Georgia Avenue and NW Kansas Avenue.
    • NW Kansas Avenue between NW Bond Street and NW Lava Road.
  • Boyd Acres Road between Brinson Boulevard and Builders Street will have frontage improvements for a private development, lane closure with lane shift, junio 9 – julio 31.
  • Proyecto de mejoras en Bear Creek y la calle 27 – Este proyecto tiene como objetivo mejorar la seguridad y la conectividad mediante la creación de rutas más seguras para ciclistas y peatones y la construcción de una rotonda en una intersección con alto índice de accidentes. Las obras comenzaron el 2 de junio y finalizarán en otoño de 2025.
    • Roundabout construction at the intersection of NE Bear Creek and NE Purcell Boulevard will begin the work, full closure with detour during its duration.
  • NW Crossing Farmers Market (special event) – special event occurring every Sábado Mayo 31 – Octubre 11. Multiple road closures related to event (listed below).
    • NW Crossing Drive between Mount Washington Drive and NW Crossing Drive (Circle).
    • NW John Freemont between NW Ordiway Avenue and NW Fort Clatsop Street.
    • NW Fort Clatsop Street between NW Ordway Avenue and NW John Freemont Street.
  • Mejoras para peatones y ciclistas en Olney – Este proyecto instalará infraestructura actualizada para bicicletas y peatones a lo largo de Olney Avenue y Portland Avenue, entre el puente de Portland Avenue y Second Street. También se instalarán alcantarillado y tuberías principales de agua nuevas. Las obras comenzaron el 3 de febrero y finalizarán en otoño de 2025. Para obtener más información, visite el sitio web Sitio web del Proyecto de Mejoras para Peatones y Bicicletas de OlneySe producirá un cierre total de la intersección (con desvío) para comenzar el proyecto con los tramos de calle cerrados que se enumeran a continuación.
    • The intersection of NW Wall Street and NE Olney Avenue is now open to traffic.
    • Olney Avenue (al este de NW Wall Street hasta NE Second Street) permanecerá cerrada hasta el otoño de 2025.
  • Midtown Crossing Project (Second Street work) – A multiphase project that will replace the water main from Greenwood Avenue to Franklin Avenue in preparation for the full reconstruction occurring next spring. Phase 2 – 4 occurs from Octubre 21 – Spring 2025. Southbound lane closure with local access will occur in its entirety. Current road section work listed below. For more information, visit the Midtown Crossing Project website.
    • Second Street between NE Irving Avenue and NE Greeley Avenue.
  • Parkwood Court, Westview East and Newberry and Twin Lakes Sewer Project – the City of Bend Programa de conversión de fosas sépticas a alcantarillado will install public pressure and gravity sewer in these neighborhoods. Road closures will begin in junio:
    • SE Westview Drive – road closed (local traffic only) between SE Admiral Way and SE Hill Ridge Road – junio 16th through Agosto 1st.
    • Twin Lakes Loop – road closed (local traffic only) from East Lake Drive to Newberry Drive – junio 19th to junio 27th.
    • Newberry Drive – road closed (local traffic only) from Twin Lakes Loop to East Lake Drive – junio 19th to junio 27th.
  • La calle NW Harriman Street, entre NW Kearney Avenue y NW Greenwood Avenue, permanecerá cerrada al tráfico por obras de infraestructura relacionadas con el juzgado del condado de Deschutes desde el 24 de julio de 2024.
  • Intersection of Deschutes Market Road and NE Yeoman Road for roundabout construction, full road closure with detour, Abril 14th – julio 2025.
  • SE 27th Street between Stevens Road and Ferguson Road for sewer main and roundabout construction, full road closure with bypass road, Completion end of junio 2025.
    • Shoulder work along SE 27th Street, north of SE Ferguson Road for asphalt taper installation.
  • NW Mt Washington Drive between NW Shevlin Park Road and NW Shields Drive for a waterline installation, daily road closure with detour, junio 16 – 27, 8:00 a.m. – 5:00 p.m.
  • Bear Creek Road between Skyline View Drive and NE Quail Run Place, lane shift for sewer connection, junio 16-27.
  • Intersection of NW Skyline Ranch Road and Skyliners Road for roundabout construction, full road closure with detour, junio 16 – Septiembre 2.

Cierres de carreteras previstos:

  •  Fourth of julio Pet Parade (special event) – Parade will have various road closures in and around downtown (listed below):
    • NW Wall Street, entre NW Newport Avenue y NW Franklin Ave.
    • NW Riverside Boulevard entre NW Wall Street y NW Galveston Avenue.
    • Avenida NW Galveston, entre la avenida NW Tumalo y el bulevar NW Harmon.
    • NW Harmon Boulevard entre NW Galveston Avenue y NW Newport Avenue.
    • Avenida NW Newport, entre el bulevar NW Harmon y la calle NW Wall.

  • Knott Road between SE 15th Street and Raintree Court for road work, road closed to eastbound traffic with a detour in place, junio 30 – Agosto 25.

Los horarios de trabajo dependen de las condiciones meteorológicas y otros factores. Extreme siempre las precauciones en las zonas de obras. Los conductores deben utilizar las rutas de desvío designadas. Las calles residenciales cercanas son solo para tráfico local.

 

Si hay algún cierre de carretera que no figure en este informe, envíe una solicitud de servicio para notificar al ayuntamiento cualquier obra potencialmente no autorizada dentro del derecho de paso de la ciudad. Visite el Departamento de Transporte y Movilidad para enviarla.


Contacto:

Alex Pelayo, ingeniero de proyectos
541-323-8556, apelayo@bendoregon.gov

Para preguntas relacionadas con la conservación de las calles:

Paul Neiswonger, supervisor de calles
541-317-3035, pneiswonger@bendoregon.gov


Los cierres y desvíos en Bend se actualizan semanalmente en: bendoregon.gov/traffic

Encuentre más información sobre las operaciones en las calles en: bendoregon.gov/streetpreservation

Los informes semanales se pueden recibir por correo electrónico suscribiéndose a los Informes semanales sobre carreteras y tráfico en: bendoregon.gov/enews


 

Silla de ruedasInformación sobre alojamiento para personas con discapacidad

Para obtener esta información en un formato alternativo, como braille, letra grande, formatos electrónicos, etc., póngase en contacto con Jacob Larsen en el 541-647-0696 o en jlarsen@bendoregon.gov.

Ver todas las noticias