Weekly Road and Traffic Report for the Week of junio 9-15

For the Week of junio 9-15:

  •  Staats Waterline Project – Replacement of aging water lines, upgraded hydrants and stormwater infrastructure, and pavement restoration along its entirety. Daytime closures of the roadway will occur during daytime hours (7 AM – 6:30 PM), junio 9 – End of Agosto. Street closures listed below.
    • NW Staats Street between NW Georgia Avenue and NW Kansas Avenue
    • NW Kansas Avenue between NW Bond Street and NW Lava Road
  •  Pacific Crest Endurance Sports Festival (special event) – This special event includes a Triathlon, Duathlon, Aquathon, and team relays. The event will close SW Century Drive, SW Colorado Avenue, and SW Columbia Street (sections listed below). Special Event closure to take place junio 14, 2023 from 6 a.m. – 11 a.m.
    • SW Century Drive between Skyline Ranch Road and SW Donovan Avenue.
    • SW Colorado Avenue between SW Century Drive and SW Emkay Drive.
    • SW Columbia Street between SW Emkay Drive and SW Shevlin Hixon Drive.
  • Boyd Acres Road between Brinson Boulevard and Builders Street will have frontage improvements for a private development, lane closure with lane shift, junio 9 – julio 31.
  • Proyecto de mejoras en Bear Creek y la calle 27 – This project aims to improve safety and connectivity by creating safer bike and pedestrian routes and constructing a roundabout at a high-crash intersection. Work begins junio 2nd – Fall 2025.
    • Roundabout construction at the intersection of NE Bear Creek and NE Purcell Boulevard will begin the work, full closure with detour during its duration.
  • NW Crossing Farmers Market (special event) – special event occurring every Sábado Mayo 31 – Octubre 11. Multiple road closures related to event (listed below).
    • NW Crossing Drive between Mount Washington Drive and NW Crossing Drive (Circle).
    • NW John Freemont between NW Ordiway Avenue and NW Fort Clatsop Street.
    • NW Fort Clatsop Street between NW Ordway Avenue and NW John Freemont Street.
  • Intersection of Deschutes Market Road and NE Yeoman Road for roundabout construction, full road closure with detour, Abril 14th – julio 2025.
  • City of Bend Street Paving – The City of Bend Transportation and Mobility Department (TMD) will be doing some street paving on Bend’s westside. Expect road closures with local access for the duration of work. Work is anticipated to begin Abril 14th. Affected Roads listed below:
    • NW 15th Street between NW Ithaca Avenue and NW Kingston Avenue.
    • NW Jacksonville Avenue between NW 15th Street and NW Kingston Avenue.
    • NW Lexington Avenue between NW 14th Street and NW Kinston Avenue.
    • NW Union Avenue between NW Newport Avenue and NW Lexington Avenue.
    • NW Cumberland Avenue between NW 14th Street and NW 15th Street.
  • Mejoras para peatones y ciclistas en Olney – This project will install updated bicycle & pedestrian infrastructure along Olney Avenue and Portland Avenue between the Portland Avenue bridge and Second Street. Replacement sewer and water mains will also be installed with this project. The work began Feb. 3 – Fall 2025. For more information, visit the Sitio web del Proyecto de Mejoras para Peatones y Bicicletas de OlneySe producirá un cierre total de la intersección (con desvío) para comenzar el proyecto con los tramos de calle cerrados que se enumeran a continuación.
    • The intersection of NW Wall Street and NE Olney Avenue is now open to traffic.
    • Olney Avenue (al este de NW Wall Street hasta NE Second Street) permanecerá cerrada hasta el otoño de 2025.
  • Midtown Crossing Project (Second Street work) – A multiphase project that will replace the water main from Greenwood Avenue to Franklin Avenue in preparation for the full reconstruction occurring next spring. Phase 2 – 4 occurs from Oct. 21 – Spring 2025. Southbound lane closure with local access will occur in its entirety. Current road section work listed below. For more information, visit the Midtown Crossing Project website.
    • Second Street between NE Irving Avenue and NE Greeley Avenue.
  • La calle NW Harriman Street, entre NW Kearney Avenue y NW Greenwood Avenue, permanecerá cerrada al tráfico por obras de infraestructura relacionadas con el juzgado del condado de Deschutes desde el 24 de julio de 2024.
  • SE 27th Street between Stevens Road and Ferguson Road for sewer main and roundabout construction, full road closure with bypass road, Completion end of junio 2025.
    • Shoulder work along SE 27th Street, north of SE Ferguson Road for asphalt taper installation.

Cierres de carreteras previstos:

  • Hunnel Road between NW Henry Avenue and NW Robal Lane for service installations, single lane closure with flagging, junio 23 – 26, 8:30 a.m. – 4 p.m..
  • Criterion Race Series (special event) – This special event is a five-week race event occurring every Miércoles from junio 25 – julio 23. The event will close a few NW City streets (listed below). A detour will be in place for the event.
    • NW Sacagawea Lane between NW John Freemont Street and NW Meriwether Place.
    • NW John Freemont Street between NW Sacagawea Lane and NW High Lakes Loop.
    • NW High Lakes Loop between NW John Freemont Street and NW Meriwether Place.
    • NW Meriwether Place between NW Sacagawea Lane and NW High Lakes Loop.
  • NW Mt Washington Drive between NW Shevlin Park Road and NW Shields Drive for a waterline installation, daily road closure with detour, junio 16 – 27, 8 a.m. – 5 p.m.

Los horarios de trabajo dependen de las condiciones meteorológicas y otros factores. Extreme siempre las precauciones en las zonas de obras. Los conductores deben utilizar las rutas de desvío designadas. Las calles residenciales cercanas son solo para tráfico local.

 

Si hay algún cierre de carretera que no figure en este informe, envíe una solicitud de servicio para notificar al ayuntamiento cualquier obra potencialmente no autorizada dentro del derecho de paso de la ciudad. Visite el Departamento de Transporte y Movilidad para enviarla.


Contacto:

Alex Pelayo, ingeniero de proyectos
541-323-8556, apelayo@bendoregon.gov

Para preguntas relacionadas con la conservación de las calles:

Paul Neiswonger, supervisor de calles
541-317-3035, pneiswonger@bendoregon.gov


Los cierres y desvíos en Bend se actualizan semanalmente en: bendoregon.gov/traffic

Encuentre más información sobre las operaciones en las calles en: bendoregon.gov/streetpreservation

Los informes semanales se pueden recibir por correo electrónico suscribiéndose a los Informes semanales sobre carreteras y tráfico en: bendoregon.gov/enews


 

Silla de ruedasInformación sobre alojamiento para personas con discapacidad

Para obtener esta información en un formato alternativo, como braille, letra grande, formatos electrónicos, etc., póngase en contacto con Jacob Larsen en el 541-647-0696 o en jlarsen@bendoregon.gov.

Ver todas las noticias