Weekly Road and Traffic Report for the Week of Mayo 20 – 26
For the Week of Mayo 20 – 26:
- NE 18th Street between Sockeye place and NE Montana Way will have a franchise utility installation, single lane closure with lane shifts.
- Awbrey Butte Waterline Improvements Project, Phase 1 – This project will provide water distribution system upgrades to the Awbrey Butte area with eight interrelated water improvement subprojects. For more information, visit the Awbrey Butte Waterline Improvements Project website.
- Saginaw Avenue: Local access only from College Way to West Hills Avenue.
- Trenton Avenue: Local access only from NW 12th Street and NW Juniper Street for sewer improvements.
- Mount Washington Drive and Shevlin Park Road roundabout: Partial Closure Mayo 14 through junio for roundabout reparation.
- Phase 1 closure Mayo 14 through Mayo 28.
- Northbound Mount Washington Drive closed south of roundabout.
- Eastbound Shevlin Park Road closed east of roundabout.
Ongoing Closures:
- Wilson Corridor Improvements Project – Street improvements on Wilson from Second Street to 15th Street. For more information visit the Wilson Project website. This is a multiphase project with various intersections and road closures throughout its entirety. Roadway to reopen Mayo 21.
- Wilson Avenue between SE Second Street and SE Third Street has a westbound closure with detour.
- Wilson Avenue between SE Third Street and SE Fourth Street has a full road closure with detour.
- Beginning Febrero 8, there will be no left turn lanes in any direction at this intersection.
- Third Street traffic will be shifted to one lane between SE Railroad Street SE Taft Avenue. Please note, blue cones are directing business access.
- Silver Sage Sewer Project – The yearly project includes installing gravity sewer mains and sewer laterals to allow properties to decommission their septic systems and connect to the public sewer system. Tentatively starting on Mayo 6, 2024: Silver Sage Street, Benham Road between Murphy Road and Rae Road, Concho Street, Loy Lane and the North-end of Tapadera Street will be closed with tentative plans for reopening in mid-Octubre 2024. Project began Mayo 1, 2024. For more information, visit the Silver Sage Sewer Project webpage.
- Pinehaven/Woodhaven Sewer Project – The yearly project includes installing gravity sewer mains and sewer laterals in order to allow properties to decommission their septic systems and connect to the public sewer system. Full road closures with local access along the full length Pinehaven and Woodhaven Avenues. Project began Marzo 11. For more information, visit the Pinehaven and Woodhaven Sewer Project webpage.
- Knott Road between SE 15th Street and Raintree Court for a watermain relocation, single lane closure with flagging, began Abril 8.
- Parrell Road between Badger Road and Rae Road for a sewer main installation, full road closure with detour, Abril 8 – Mayo 24.
- Brosterhous Road between Kobe Street and Frankie Lane will have a sewer main installation, full road closure with detour, begins Abril 29 – Mayo 24.
- Brosterhous Road between Button Brush and songbird lane for frontage improvements, single lane closures with flagging and possible lane shifts, begins Abril 3.
- SW 18th Street between SW Simpson Avenue and SW Forest Ridge Avenue for infrastructure improvements, full road closure with detour, began Marzo 25.
- Jamison Street between Empire Avenue and Poe Scholes Drive for a gas main relocation, full road closure with detour, began Marzo 25.
- Bend North Corridor, ODOT Project – Infrastructure improvements along Highway 97 from Empire Avenue to Grandview Drive. Highway 97 will also be realigned to allow free flowing movement. Various types of traffic control will be implemented during construction. Expect additional delays throughout this segment of the corridor. Expected to be completed by the end of 2024.
- Empire onramp northbound will be redirected toward the newly built Highway 97 and connected to the existing Highway 97 at Robal Road, begins Abril 8.
- Cooley Road between Highway 20 and Hunnel Road for infrastructure and roadway improvements, full road closure with detour, began Dec. 26.
Cierres de carreteras previstos:
- Parrell Road between Vassar Place and Rocca Way will have a sewer service installation, single lane closure with flagging, junio 3 – 6, 8:30 a.m. – 4 p.m.
Los horarios de trabajo dependen de las condiciones meteorológicas y otros factores. Extreme siempre las precauciones en las zonas de obras. Los conductores deben utilizar las rutas de desvío designadas. Las calles residenciales cercanas son solo para tráfico local.
Si hay algún cierre de carretera que no figure en este informe, envíe una solicitud de servicio para notificar al ayuntamiento cualquier obra potencialmente no autorizada dentro del derecho de paso de la ciudad. Visite el Departamento de Transporte y Movilidad para enviarla.
Contacto:
Deedee Fraley, Assistant City Engineer
541-385-6199, dfraley@bendoregon.gov
Para preguntas relacionadas con la conservación de las calles:
Paul Neiswonger, Streets Supervisor
541-317-3035, pneiswonger@bendoregon.gov
Los cierres y desvíos en Bend se actualizan semanalmente en: bendoregon.gov/traffic
Encuentre más información sobre las operaciones en las calles en: bendoregon.gov/streetpreservation
Los informes semanales se pueden recibir por correo electrónico suscribiéndose a los Informes semanales sobre carreteras y tráfico en: bendoregon.gov/enews