Weekly Road and Traffic Report for the Week of Sept. 27 – Oct. 3
For the Week of Sept. 27 – Oct. 3:
- NW Jamison Street between Empire Avenue and Halfway Road for work related to the CSEP project, single lane closures with flagging, begins 7/28/21
- Pump Station Decommissioning – This project will decommission the Tri-Peaks, Shire, and Desert Skies Pump Stations. Full road closures with local access only on affected streets beginning on 7/19/21. For further information, visit bendoregon.gov/city-projects/what-s-being-built/pump-station-decommissioning-phase-3.
- Clairaway Avenue between 27th Street and Daly Estates Drive
- Daly Estates Drive between Clairaway Avenue and the desert skies pump station
- Chase Rd from Benham Rd towards the east will be closed beginning Lunes 8/23/21
- Benham Road between Chase Road and Knightsbridge Place
- NW Silver Buckle Road – As part of the Rimrock Pump Stations Improvement project, full road closure during work hours 7 am – 6:30 pm. Roadway to be fully reopened at end of each workday and intermittently opened during each workday at 10 am and 2 pm; 7/19/2021 – 11/19/2021.
- NW Crossing Farmers Market – special event occurring every Sábado 6/5/21 – 10/16/21. Multiple road closures related to event (listed below).
- NW Crossing Drive between Mount Washington Drive and NW Crossing Drive (Circle)
- NW John Freemont between NW Ordiway Avenue and NW Fort Clatsop Street
- NW Fort Clatsop Street between NW Ordway Avenue and NW John Freemont Street
- NE Butler Market – Purcell Intersection – closed for roundabout construction beginning Mayo 3rd – early Octubre. This is part of the Empire Corridor Improvements Project. For further information, visit bendoregon.gov/empire.
- NW Broadway Street between NW Louisiana Avenue and NW Kansas Avenue for water main replacement, full road closure with local access, 6/1/21 – Early Octubre
- NW Tumalo Avenue between NW Broadway Street and NW Riverside Boulevard for water main replacement, full road closure with local access, 9/20/21 – Late Octubre
- Newport Corridor Improvements Project – Various intersections along Newport Avenue to be closed due to updates in the water main and stormwater facilities. Road closures related to the project listed below.
- Intersection of 9th Street and Newport Avenue for infrastructure installation, full roundabout closure with detour, 4/5/21 – Early Octubre
- Newport Avenue – east of the NW College Way roundabout through NW Juniper Street, full closure with detour, 8/2/21 – Early Spring 2022. Businesses within the closure are still open and accessible.
Cierres de carreteras previstos:
- NW Wall Street between NW Portland Avenue and NW Deschutes Place for an infrastructure installation related to CSSP, southbound lane closure with detour, Octubre 4 – mid-noviembre
Los horarios de trabajo dependen de las condiciones meteorológicas y otros factores. Extreme siempre las precauciones en las zonas de obras. Los conductores deben utilizar las rutas de desvío designadas. Las calles residenciales cercanas son solo para tráfico local.
Contact: Deedee Fraley, Right of Way & Construction Manager
541-385-6199, dfraley@bendoregon.gov
For Street Preservation related questions: Paul Neiswonger, Streets Supervisor
541-317-3035, pneiswonger@bendoregon.gov
Los cierres y desvíos en Bend se actualizan semanalmente en: bendoregon.gov/traffic
Encuentre más información sobre las operaciones en las calles en: bendoregon.gov/streetpreservation
Los informes semanales se pueden recibir por correo electrónico suscribiéndose a los Informes semanales sobre carreteras y tráfico en: bendoregon.gov/enews
Información sobre alojamiento para personas con discapacidad

To obtain this information in an alternate format such as Braille, large print, electronic formats, etc. please contact Anne Aurand at 541-388-5573 or aaurand@bendoregon.gov.
Ver todas las noticias