Estado del proyecto

Plan
Diseño
Construir
Completo

Fecha estimada de finalización

Por determinar

Contacto

Imagen tomada desde un dron del este de Bend, con Pilot Butte a lo lejos.

Avenida Franklin


PHASE 2 UPDATE – Additional Closure Scheduled Sept. 1-3 for Paving Work

  • Martes, Sept. 1 – Paving on Franklin Avenue from Third Street to Fourth Street
    Requires eastbound traffic closure (7 a.m. to 7 p.m.)
  • Miércoles, Sept. 2 – Paving on South side of Franklin Avenue from Fourth Street to Eighth Street
    Requires eastbound traffic closure (7 a.m. to 7 p.m.)
  • Jueves, Sept. 3 – Paving North side of Franklin Avenue from Fourth Street to Eighth Street
    Requires westbound traffic closure (7 a.m. to 7 p.m.)
  • A detour will be in place on NE Third Street, Greenwood Avenue, and NE Eighth Street.

    After paving, eastbound closure continues

    • EASTBOUND CLOSURE: Franklin Avenue from Third Street to Fourth Street, one-way westbound travel only
    • START DATE: Lunes, agosto 17
    • DETOUR ROUTE: Third Street to Greenwood Avenue to Eighth Street

    Westbound Closure Continues

    • WESTBOUND CLOSURE: Franklin Avenue from Second Street to Third Street, one-way eastbound travel only
    • START DATE: Lunes, agosto 3
    • DETOUR ROUTE: Third Street, Greenwood Avenue, and Wall Street

    Traffic patterns will change frequently on Franklin through mid-septiembre – sign up for the weekly road report at bendoregon.gov/traffic.

    JOIN US FOR COFFEE WITH THE CONTRACTOR – SEPT 1

    Stop by to ask questions and learn more about the upcoming temporary closure of the Franklin Avenue underpass.

    • Martes, septiembre 1
    • 8:00-10:00 a.m.
    • 182 NE Franklin Avenue in Parking Lot – enter from Second Street

    MÁS INFORMACIÓN SOBRE LOS HORARIOS Y EL MAPA DE DESVÍOS A CONTINUACIÓN

    Las fechas son estimadas y están sujetas a cambios.

Reuniones públicas

Novedades del proyecto Midtown